Back To Work
Now that the snow is gone, they are back at it to finish up the year.
Friday, December 19, 2008
Snow Delay
We are in a delay because of the weather. There has been snow on the work site for over and week and it looks like we'll get more before Christmas.
Friday, December 12, 2008
First Floor
Tuesday, December 9, 2008
Basement is Framed.
Main floor is starting tomorrow.
Monday, December 8, 2008
Janette's Turn to Pick......Again.
Friday, December 5, 2008
Basement Walls
A lot of back fill and dirt got pushed around too.
Wednesday, December 3, 2008
Basement Floor
Basement floor and some back fill today. Tomorrow the framing starts.
Thanks Paul.
Tuesday, December 2, 2008
Got Sticks.
The rest of the week should be busy with the basement floor tomorrow then the framing starts.
Monday, December 1, 2008
Janette's Turn to Pick.
Today we looked at flooring, counter tops, and tile for the
back splashes
and shower.
Rain Delay
Basement floor to be poured on Wednesday.
Newer Posts
Older Posts
Home
Subscribe to:
Posts (Atom)
The Goal
One day we'll live here.
Blog Archive
►
2009
(66)
►
May
(3)
Living Out of Boxes
We're MOVING!!!!!!!!!
Final Inspection
►
April
(13)
All but the Paperwork.
Wrapping Up
Random Requests
No wire hangers!
Dog's Life.
knick knacks, Dustables, and Hootenanny's
Bring on Summer
Finales
Plumbing
Paint Preview
Making the Grade
Emma's Room
Floors and Desk
►
March
(17)
Tile and Floors
Tile Work
We are ready to move in.....
Floors and Counter Tops
Lighting
Cabinets are going in
Paint and Cabinets
Paint
Little by Little
What's Happening.
Siding Done
Walkabout
Mud
Garage Floor
Almost done with the siding.
Drywall is Up
We Have Permanent Power
►
February
(14)
Lets Rock
Emma Was Here.
Warming Up
Siding
Walkabout
Ready for Inspection
Rough In Wrap Up
There is a lot going on.
Random Pictures of Stuff
It Stopped Growing
Siding
Plumbers Rule
Random Pictures
Dried-In
►
January
(19)
Shingles
Shingle Poll
Wrap up work.
▼
2008
(23)
▼
December
(10)
Back To Work
Snow Delay
First Floor
Basement is Framed.
Janette's Turn to Pick......Again.
Basement Walls
Basement Floor
Got Sticks.
Janette's Turn to Pick.
Rain Delay
►
November
(5)
►
October
(8)
About Me
Mark Bowers
View my complete profile
E-Mail me at......
What's the Weather
My personal weather station uploaded every 10 minutes from my house.